FULL
BOARD MEETING
Services Building Conference Room
Saturday, November 18, 2000
MINUTES
The Fernald Citizens Advisory Board met from 8:35 a.m. until 12:15 p.m.
on Saturday, November 18, 2000, at the Fernald Site Services Building
in Hamilton, Ohio. The meeting was advertised in local papers and
was open to the public.
Members
Present
French Bell
Jim Bierer
Sandy Butterfield
Marvin Clawson
Lisa Crawford
Steve Depoe
Lou Doll
Pam Dunn
Gene Jablonowski
Jane Harper
Graham Mitchell
Robert Tabor
Thomas Wagner
Members
Absent
Fawn Thompson
Mike Keyes
Gene Willeke
Phoenix
Environmental Staff
Douglas Sarno
Patti Kidd
Designated Federal Official
Johnny Reising
Approximately
10 spectators also attended the meeting, including members of the
public, the media, and representatives from the Department of Energy
and Fluor Fernald.
1. Call to Order
Jim Bierer called the meeting to order at 8:35 a.m.
2. Remarks and Announcements
The FCAB received a letter acknowledging its Stewardship recommendations
and an update on progress at the site. Graham Mitchell led a discussion
about damage to trees on site that is being caused by deer. A plastic
protective covering has been used on the trees, but the damage is continuing.
Since tree replacement is a financial burden, other methods are being
considered such as deer population monitoring and control. Members voiced
some concerns about hunting as a control method. No specific actions
are to be immediately taken other than monitoring the situation.
DOE Headquarters has approved moving forward on the reinterment of Native
American Remains.
The cattle grazing lease will be renewed; however, acreage will be reduced
from 60 acres to 37 acres. If additional land is needed for Native American
reinterment, grazing can be eliminated upon 45 days notice to the lessee.
3. Report on SSAB Stewardship Workshop
Pam Dunn led a discussion on the draft recommendations on long-term stewardship
that were developed at the workshop. The purpose of the recommendations
are to ensure that long-term stewardship for contaminated sites is a
major focus of DOE. Each SSAB is being asked to endorse all of the recommendations.
The recommendations are categorized by funding, roles and responsibilities,
timing of stewardship, information management, and public involvement.
After discussion of possible improvements, it was decided to endorse
the recommendations as written.
Jim Bierer moved that the recommendations be endorsed and notification
sent to the other boards. The motion passed unanimously.
4. Update on Contract and Budget Issues
A new support contract for the Fernald site will be authorized and signed
on Monday, November 20, 2000. There will be a six month period to reestablish
the baseline and to plan for site closure. There will be a briefing of
the new contract at the January meeting and updates at each meeting thereafter
for six months.
On October 27, 2000 the budget was issued for fiscal year 2001 and the
first allotment has already been issued. The budget results in a $23
million shortfall for Fernald. There will be a rebaselining to accommodate
the shortfall and to keep all projects moving forward. The FCAB will
be kept up to date regarding the schedule impacts of this shortfall.
5. WPRAP Update and Discussion
Dave Lojek of DOE briefed the FCAB on the Waste Pits Remedial Action
Project. The overview included key remediation dates, material flow,
project successes and achievements, current excavation status, and radiological
airborne issues and status.
Approximately 1,000,000 tons of low-level radioactive and contaminated
subsoils will be excavated. Approximately 300,000 tons of moisture will
be removed from the waste resulting in approximately 626,500 tons of
materials to be transported offsite for disposal. It was noted that the
moisture content of materials being shipped to Envirocare has been consistently
higher than estimated. While within acceptable limits for disposal, this
higher moisture content results in more weight of material and higher
disposal costs. The FCAB asked to be kept informed of efforts to manage
this issue and any resulting impacts on the project.
To date, 100% of the contract quantity for operational year one was met,
and 90% of the contract for operational year two was met. All EPA enforceable
milestones have been met: 1,680 railcars have been loaded, and 29 unit
trains have been shipped. The project is on track for operational year
three. There have been 1,100 days without a lost-time accident and one
year without an OSHA recordable event. The project has received the IT
Group Presidential Award, the IT Group Quarterly Award, and the Fluor
Tri-Star Award.
Currently, excavation in Pit 1 is 30% complete, Pit 2 excavation will
start in Spring 2001, Pit 3 is 30% complete, Pit 4 will start in Summer
2001, and Pit 5 test excavations were performed with full excavation
to start in Spring 2001.
A map of air sampling locations was presented and the air-monitoring
system was explained. In certain areas where airborne contamination is
elevated, 50,000 lapel air samplers have also been used to study air
contamination. Airborne contaminants were detected in an area not previously
monitored showing high levels of Thorium 230. A detailed plan was developed
to identify the cause of this contamination. Goals are to determine sources
and potential sources, administrative and engineering controls necessary
to abate the sources, and the effectiveness of the current monitoring
program. Testing is underway and will be completed in four to five weeks.
Normal operations will not proceed until testing is complete. The FCAB
asked to be kept informed of this issue.
6. Silos Update and Discussion
Discussion with the current contractor is ongoing but it has not produced
anything of substance. Within the next two weeks, a decision will be
made whether or not to stay with the current contractor. If the current
contractor decides to perform, there are obvious concerns about its ability.
On the other hand, there are no current backup plans. Any change will
certainly result in cost and schedule impacts. The FCAB asked to be kept
apprised of the situation.
The FCAB also expressed concern about getting updates and reports from
Fluor, DOE and the CAT Team in a timely manner. The CAT Team assured
the FCAB that all involved parties will receive prompt reports on progress
from now on.
7. New Member Recruitment
There are two openings on the board. The board reviewed a new member
solicitation fact sheet and discussed what kind of person(s) would be
needed. It was suggested that one of the new members be a high school
or college student. A discussion followed on how to recruit a student
board member through the local high school or college.
8. Public Comment
Jim Bierer opened the floor to public comment. There was none.
9. Adjournment
Jim Bierer adjourned the meeting at 12:15 p.m.I certify that these minutes
are an accurate account of the November 18, 2000 meeting of the Fernald
Citizens Advisory Board.
James Bierer, Chair Date
Fernald Citizens Advisory Board
Johnny Reising Date
Deputy Designated Federal Official
|